Construction Update January 2023

Screenshot 2023-01-05 135913
  1. Demolition works at the fuel depot (in the Southern SANG) will continue in January. We will also continue crushing materials so they can be reused, during this time the team will be monitoring noise at the site boundary.
  2. We will continue to demolish military support buildings throughout the Southern SANG to make way for the construction works.
  3. We will maintain progress on the Loop Road in the New Year as the team continues to install the drainage system. There will be additional traffic into Gate 1 to facilitate deliveries to the site.
  4. External refurbishment works will continue at St. Barbara’s Church. Paint has now been stripped from the building so the team can start redecorating.
  5. Landscaping maintenance will continue in the Village Green, Central SANGs and along Mindenhurst Road.

What else is on

Upcoming Resurfacing Works on Deepcut Bridge Road
27/03/2025
Upcoming Resurfacing Works on Deepcut Bridge Road
We will shortly carry out resurfacing works on Deepcut Bridge Road...
Public Art: From Concept to Creation
10/02/2025
Public Art: From Concept to Creation
Introducing Tom Pearson, the talented artist commissioned to create three...

Sign up to our mailing list

Keep up to date with the latest news and events, as well as construction progress by signing up for our digital newsletter.