Construction Update - December 2021

Please find below the latest construction update.

Construction Update - December 2021

1 – Landscaping works will be continuing on the Eastern landfill which includes planting and seeding.

2 There will be ongoing works to the ‘Bovis Bank’ which is located at the top of Royal Way. This includes removal of contaminated ground and replacement with topsoil and planting. These works will continue into the New Year when our landscaping contractor will take over to seed and plant in this area.

3 – Landscaping works have now recommenced on the Green Swathe following the remediation that took place in November. Contractors are working in the area installing the new footpaths and infilling the area with topsoil suitable for landscaping works to follow.

4 – Works will commence on the Cala access for Parcel M2 – this is the access just outside of the current Princess Royal Barracks main entrance. These works will involve kerb and road realignment and installation.

Construction Update - November 2021

Construction overview

Summary of progress in 2021

• Progress with the SANGs and green infrastructure.

• Began pub construction.

• Public consultation on remaining infrastructure Reserved Matters.

• Affordable Housing resolved.

• Infrastructure delivery.

Spring 2022

• The official pub opening.

• Loop Road works will commence,
subject to planning.

• Determination of all infrastructure
Reserved Matters Application.

What else is on

Strava Step Count Challenge
20/10/2023
Strava Step Count Challenge
Enjoy walking? Why not take part in the Mindenhurst Step Count Challenge! 
Lakeside School Feeling Good Week
19/10/2023
Lakeside School Feeling Good Week
The Mindenhurst team supports newest members of the community, Lakeside School

Sign up to our mailing list

Keep up to date with the latest news and events, as well as construction progress by signing up for our digital newsletter.