Construction Update - April 2022

Please find below the latest construction update.

Construction Update - January 2022

1 – We will be installing a new substation and electrical cables on Blackdown Road. There will not be any road closures due to these works.

2 Refurbishment works to St. Barbara’s church will continue. This includes the installation of scaffolding to facilitate weatherproofing and decoration works. We will be closing off some of the parking spaces in the church car park, on the left-hand side as you enter. This will be our compound area and will allow us to conduct works without blocking access for pedestrians.

3 Landscaping works will be continuing to the Green Swathe, including the installation of the new pedestrian bridges.

4 – We will start demolition of the buildings within Princess Royal Barracks that are situated on the path of the new Loop Road. This new road will run behind the Mindenhurst School therefore there will be additional noise in the area. Dust and noise levels will be closely monitored during these works.

 

Construction Update - April 2022

What else is on

Strava Step Count Challenge
20/10/2023
Strava Step Count Challenge
Enjoy walking? Why not take part in the Mindenhurst Step Count Challenge! 
Lakeside School Feeling Good Week
19/10/2023
Lakeside School Feeling Good Week
The Mindenhurst team supports newest members of the community, Lakeside School

Sign up to our mailing list

Keep up to date with the latest news and events, as well as construction progress by signing up for our digital newsletter.