Construction Update December 2022

Screenshot 2022-11-30 174955
  1. We will refill the trench on Blackdown Road and reopen the footpath before the Christmas period.
  2. There will be an increase in site traffic as we continue with the demolition of the Fuel Depot in the Southern SANG.
    Residents who live nearby will receive further information. As always, our team will closely monitor noise levels and stay within the agreed working times.
  3. The team is progressing the Loop Road construction works and in coming weeks we will be starting work on the drainage system. There will be some additional traffic to deliver machinery and materials to support these works. Our refurbishment of St. Barbara’s Church continues, the next stage of work includes repairs and external painting.
  4. Our landscaping team will carry out maintenance along the Village Green, Central SANGs and Mindenhurst Road.

What else is on

Christmas Tree Recycling
16/12/2024
Christmas Tree Recycling
Don’t forget to drop off your Christmas tree at our recycling point after...
Christmas Elves in the Central SANG
04/12/2024
Christmas Elves in the Central SANG
We have heard reports that playful Christmas Elves are heading to the Central...

Sign up to our mailing list

Keep up to date with the latest news and events, as well as construction progress by signing up for our digital newsletter.